Get all latest (August) PMI PMI-002 Actual Test 491-500

QUESTION 491 The project manager's leadership style should be matched to the corresponding developmental level of the project team and should move through successive steps in the following order:   A. Disciplinary, autocratic, and participative B. Staff planning, team training, and performance monitoring C. Team building, team development, and responsibility assignment D. Directing, coaching, supporting, and delegating   Correct Answer: D     QUESTION 492 When Identify Read more [...]... Read More

Get all latest (August) PMI PMI-002 Actual Test 481-490

QUESTION 481 Using the PMBOK definition of contingency reserve, which of the following statements about contingency reserves is false?   A. A contingency reserve is a separately planned quantity used to allow for future situations which may be planned for only in part. B. Contingency reserves may be set aside for known unknowns. C. Contingency reserves may be set aside for unknown unknowns. D. Contingency reserves are normally included in the project's cost and schedule baselines. Read more [...]... Read More

Get all latest (August) PMI PMI-002 Actual Test 471-480

QUESTION 471 Completion of the _____________ scope is measured against the project management plan.   A. Project B. Technical C. Product D. Baseline   Correct Answer: A Explanation: A is the correct answer. Completion of the Project scope is measured against the project management plan.     QUESTION 472 Developing a written scope statement as the basis for future project decisions is called _________________.   A. Product Analysis B. Define Scope C. Read more [...]... Read More

Get all latest (August) PMI PMI-002 Actual Test 461-470

QUESTION 461 Correspondence, contract changes, and payment requests are ___________ of contract administration.   A. Outputs B. Tools C. Functions D. InPuts   Correct Answer: A     QUESTION 462 Collect Requirements includes alternatives identification, which can be conducted by the common technique of   A. Lateral thinking B. Value engineering C. Cost/benefit analysis D. Constraints analysis   Correct Answer: A     QUESTION 463 Which Read more [...]... Read More

Get all latest (August) PMI PMI-002 Actual Test 451-460

QUESTION 451 Deflection or transfer of a risk to another party is part of which of the following risk response categories?   A. Transfer B. Acceptance C. Avoidance D. Mitigate   Correct Answer: A Explanation: A is the correct answer. transfer of a risk to another party (third party) is part of Transfer strategy (Strategies for negative risks).   & nbsp; QUESTION 452 In project communications, the sender is responsible for _____________.   A. Making the information Read more [...]... Read More

Get all latest (August) PMI PMI-002 Actual Test 441-450

QUESTION 441 The sender is responsible for ____________.   A. Confirming the message is understood B. Ensuring the receiver agrees with the message C. Scheduling communication exchange D. Presenting the message in the most agreeable manner   Correct Answer: A     QUESTION 442 The overall intentions and direction of an organization with regard to quality as formally expressed by top management is a ____________.   A. Quality Plan B. Quality Statement Read more [...]... Read More

Get all latest (August) PMI PMI-002 Actual Test 431-440

QUESTION 431 Which of the following statements concerning bottom-up estimating is true?   A. The cost and accuracy of bottom-up estimating is driven by the size of the individual work items. B. Smaller work items increase both cost and accuracy. C. Larger work items increase both cost and accuracy. D. Both A and B are true   Correct Answer: D Explanation: Which of the following statements concerning bottom-up estimating is true?     QUESTION 432 A technique for resolving Read more [...]... Read More

Get all latest (August) PMI PMI-002 Actual Test 421-430

QUESTION 421 The normal risk of doing business that carries opportunities for both gain and loss is called _______________.   A. Favourable risk B. Opportunity risk C. Pure risk D. Business risk   Correct Answer: D     QUESTION 422 AON refers to __________.   A. Precedence Diagramming Method [PDM] B. Arrow Diagramming Method [ADM] C. Fragment Network D. All of the above   Correct Answer: A Explanation: A is the correct answer. PDM is also Read more [...]... Read More

Get all latest (August) PMI PMI-002 Actual Test 411-420

QUESTION 411 Group brainstorming encourages all of the following except _________.   A. Team building B. Analysis of alternatives C. Convergent thinking D. Q Uninhibited verbalization   Correct Answer: C     QUESTION 412 The three major types of communication are: ______________.   A. Written, verbal, and non-verbal B. Verbal, formal documentation, and informal documentation C. Verbal, written, and graphic D. Verbal, written, and electronic   Read more [...]... Read More

Get all latest (August) PMI PMI-002 Actual Test 401-410

QUESTION 401 Management reserves are used to handle which type of risk?   A. Unknown unknowns B. Known unknowns C. Business risks D. Pure risks   Correct Answer: A     QUESTION 402 Which of the following statements is TRUE regarding various Activity Scheduling tools?   A. PDM allows for conditional branching and iteration of activities. B. PDM uses activity-on-node (AON) diagramming method. C. PDM allows for conditional branching and iteration of Read more [...]... Read More